Lowville- The Lewis County Board of Legislators and Lowville Village Board of
    Trustees received an update this afternoon from County Director of Planning,
    Frank Pace, and Department of Public Works Superintendent Thomas Compo,
    from the Village of Lowville, on the status of the infrastructure upgrades that will be
    needed in the village in order to accommodate the expansion that Kraft Heinz has
    planned.

    The village wastewater treatment facility will need an extensive upgrade. The
    current plant is permitted to handle 1.8 million gallons of sewage per day. Kraft
    Heinz is permitted to send 750,000 gallons per day through the system and, as of
    March 1st this will be increased to 800,000 gallons per day, The rest of the village
    sends on average 350,000 - 400,000 gallons through the system each day, taking
    the total to around 1.2 million gallons.  Kraft Heinz has requested an increase to
    1.2 million gallons per day by September and 3 million gallons per day in the long
    term after the expansion is completed.

    The Village of Lowville has been working on acquiring the funding needed to
    complete an upgrade on a system that dates back to the 1930s. The Five Streets
    Project that the village has presented as some of the oldest infrastructure on the
    system includes Park Avenue, Water Street, Shady Avenue, Trinity Avenue and
    Stowe Street. The estimated $17.7 million project would upgrade water and sewer
    lines and qualifies for 0% interest, 30 year loans from the state Environmental
    Facilities Corporation (EFC). Up to $5 million of the cost can be awarded in a
    grant that has been applied for.

    A new treatment facility that would handle 4 million gallons of sewage per day is
    going to cost an additional $37 million. The new facility would use anaerobic
    digestion and would be able to increase capacity in the future by adding additional
    digesters. A digester could be added at the current facility in the interim to alleviate
    any capacity issues while the new facility is built, which would take about two
    years. The self contained, closed loop system would produce methane, which in
    turn would be turned into electricity to power the facility in the long term. Other
    interim options are being considered to obtain the most capacity on the current
    system until a new facility is online.

    No commitments have been secured for funding yet, but the view has shifted that
    the project is more regional and not just for the benefit of the village, which could
    help with additional sources. County officials have brought the urgency of the
    project to the attention of state officials recently.

    The Kraft Heinz plant in Lowville employs 343 people currently. Of that, 277 reside
    in Lewis County, with 106 of those residing in the Village of Lowville. Other
    employees reside in Jefferson, Oneida and St. Lawrence counties.

    The board was told that the new string cheese line Kraft Heinz has planned with
    their expansion will add 125 jobs over the next five years, with an additional 25
    jobs expected with increased cream cheese production. These jobs would add an
    estimated $9.4 million in salaries to the region annually. The year long
    construction project at Kraft Heinz is expected to employ 139 workers.
Kraft Heinz Expansion Project Will Require
Additional Infrastructure Upgrades in Lowville
02/09/16 08:45pm
Copyright 2015 linkinglewiscounty.com  all rights reserved       privacy policy here
Everything
You Need To
Know About
Lewis County
In One Place!
This Prime Ad Space is
Available!
Contact Us!
Like us on Facebook
Search Our Site:
Tax time is here again! Get
the most from your return!
Contact Noftsier's Tax
Service for all of your tax
and financial service needs!
Village of Lowville Wastewater Treatment Facility Plan With Four Digesters