Railroad Abandonment Delay Slows Down County Purchase
Effort
Published: February 19, 2024
at 11:30 a.m.
By: Julie Abbass
Railroad Abandonment Delay Slows Down County Purchase
Effort
Lowville, NY- Lewis County’s
purchase of long out-of-use rail lines for conversion into recreational
trails has been delayed as the federal Surface Transportation Board has
more questions for the two lines’ owner, Genesee Valley Transportation
(GVT).
The company’s
railroad “abandonment,” needed for the sale to go through, was paused on
January 22 with the board’s decision requesting more information and
additional steps.
This was the
transportation board’s second decision since GVT filed an “exempt”
abandonment application on September 11, 2023 for
the Mohawk, Adirondack & Northern line from Lowville to Carthage and
the Lowville & Beaver River Railroad line from Lowville to Croghan.
The “exempt”
designation, according to the federal laws governing railway abandonment,
is a more expedited process allowed for railroads that have been out of use
for at least two years and owned by the company applying to abandon the
track for at least two years, among other criteria.
In their
application, GVT stated that the two lines have been out of use for “at
least 15 years,” which has not been disputed by the board, however, the
board questioned the “ownership” of the Lowville & Beaver River
Railroad which was transferred from the Lewis County Industrial Development
Corporation back to GVT in 2016 after their “payment in lieu of taxes”
(PILOT) agreement ended without the permission of the transportation board.
The board had
approved the original 1991 transfer into the IDA’s name when the PILOT
agreement began.
The company’s
lawyer, John Fiorilla, of Dyer & Peterson in New Jersey and County
Manager Ryan Piche confirmed in interviews that the transfer was standard
practice for PILOT agreements and was done in name only. It did not impact
the operation, maintenance or responsibilities of
the rail lines.
In their January decision, the board stated the company will have
to request “after-the-fact authority to acquire the line” which would mean
the company would no longer meet the exemption requirements because they
would not have owned the railway at least two years.
The work-around
provided by the board requires GVT to request a waiver for that particular requirement.
Mr. Fiorilla said
that the board’s questions are typical for this type of proceeding, and he
is confident that the abandonment request will ultimately be approved.
“Once we got all of the objections, they (the board) want to dot all the i’s and cross all the t’s and that’s fine.
That’s what they do,” said Mr. Fiorilla. “I can’t picture them not allowing
an abandonment here. We meet every requirement that they have and without
any trains or customers for 15 years– that’s a long time.”
About 15 comments
from county residents and municipalities were filed speaking out against
the abandonment for various reasons including anticipated impacts on
agriculture, flooding concerns, track and contaminated soil removal and
tribal lands. The board said these will be addressed through the
environmental and historic review that will take place once the abandonment
process continues.
Some filings by
the Railway Historical Society of Northern New York, Croghan, and Rail Star
rail bike company– both of which are owned by Ronald J. Trottier, Cape
Vincent– were included specifically in the decision. Trottier has long
spoken of his intention to rent the Lowville to Carthage tracks for rail
bikes and a tourist railroad and had brought an engine to Lowville a few
years ago toward that end.
The board denied
the historical society’s October “request for a stay of the abandonment
proceedings” and sided with GVT’s claim that Rail Star’s filing of an
“Offer of Financial Assistance” did not include the required information
about the type of financial assistance the company would like to provide
the railroads and proof their financial situation can support such an
offer.
In response to
the historical society’s assertions that the entire Lowville & Beaver
River Railroad line and a number of adjacent
buildings are eligible for the National Historical Registry, the board
required GVT to provide information about all of the structures that exist
that are included in the sale to Lewis County and potentially eligible for
historic status.
GVT had provided
a copy of a letter they sent to the state Historical Preservation Office
inviting representatives to come in person to view the tracks, bridges and
structures involved with the sale, noting they had not received a response.
The company was
also asked to provide additional information about the track and soil
removed by Lewis County last summer, though GVT had already provided
information about the lawsuit they had filed against the county for doing
so without permission, the settlement of which was part of the sale
negotiation with the county.
GVT is required
to provide more clear, accurate and detailed maps of both lines, including
the Beaver River spur from Croghan which was not included in the map
provided in the original application, showing any land or buildings next to
the railway that would be part of the sale and clarified endpoints and
mile-markers.
Because the
Lowville to Carthage line is “the only connection to the national rail
network” for the Lowville to Croghan line, the board made clear that the
abandonment of the Carthage line is dependent on the success of the Croghan
line bid.
The Mohawk,
Adirondack & Northern company and the Lowville & Beaver River
Railroad are both owned by GVT and are the names that appear in the
abandonment process, not that of GVT.
According to
GVT’s original filing, the exempt abandonment process was expected to take
about 50 days which would have been at the end of October.
“It’s very
frustrating that this process has taken so long. The abandonment process is
between the railroad owners and the Surface Transportation Board, so the
county, other than being an interested bystander, is not really involved in
this process,” said Mr. Piche. “In particular it’s frustrating because
there’s a thirst from the public for information about this and this delay
makes it seem like there is more happening behind the scenes than there
really is.”
Mr. Piche said
the consultant hired by the county last year to help with the Rails to
Trails project is at this time only focused on “economic analysis” and
basic branding of the trail project, including public information sessions,
that will launch when the abandonment and sale are complete.
After GVT files all of the requested information for each railway line
with the Surface Transportation Board and those participating in the
process, there will be a 20-day public comment period before the board will
allow the abandonment process to proceed, including their environmental and
historic review process.
As of February
18, GVT had not yet filed its response to the board’s decision.
|