| Work Underway on Route 812 Culvert Replacement; Project Should be Completed by July 4th Weekend June 19, 2019 02:15 p.m. |
| Subscribe to our YouTube Channel |
project now that the weather has improved and the water has receded. State Department of Transportation (DOT) crews expect to have the pipe bedded with backfill ongoing the remainder of this week. "While working at the location, we discovered another pipe inside the closure area that, while not in as bad of shape as the one we are replacing, needs work," Michael Flick, Regional Public Information Officer with NYS DOT told linkinglewiscounty.com today. "We will be slip-lining this pipe and doing some remediation to the inlet/outlet ends." Mr. Flick said both sites are expected to be completed in the coming weeks and anticipates that Route 812 will be reopened to traffic by the July 4th weekend. (Photos provided by Mr. Flick) |